VAP Audit Scheduling, Bidding, and Audit Firm Assignment: What to Expect

Table of Contents

Quick answer: Is my requested audit date confirmed? Understanding the scheduling process What this means for facilities Who selects the assessment firm? Can a facility request a specific assessment firm? Can an assessment firm offer available assessors or dates? Who assigns the individual assessors? What happens during bidding? What happens if the requested dates are no longer available? What does it mean if a bid has expired? When might bidding need to be reopened? What if the bid was already accepted? Can the assessment firm be changed after assignment? What if I need to reschedule a confirmed assessment? What if the date shown in RBA Online appears incorrect or expired? Special consideration for semi-announced or unannounced assessments How do I know when scheduling is complete? Proposed date Firm availability Bid selected Audit Dates Finalized Scoping Agreement completed What information should I provide when requesting scheduling assistance? If you represent an assessment firm Example requests Confirming a date Requesting rescheduling Assessment firm advising availability Frequently asked questions I entered a requested date when initiating the VAP. Is that my confirmed audit date? Can I choose the assessment firm? Can I choose a specific assessor? An assessment firm says it has assessors available. Does that mean the audit is confirmed? Can bidding be reopened? Can an assessment firm be changed after selection? Does changing the audit date affect the Scoping Agreement? Could changing the date result in additional fees? Need help?

Scheduling a Validated Assessment Program (VAP) assessment involves coordination between the facility, RBA, and an approved assessment firm. The process includes scoping the assessment, obtaining bids, selecting an assessment firm, finalizing audit dates, and completing the applicable Scoping Agreement.

A date requested during audit setup should be understood as a preferred or requested assessment window, rather than confirmation that the assessment has been scheduled. 

This article explains:

  • How requested and confirmed audit dates differ
  • How assessment firms are selected
  • Who assigns individual assessors
  • What happens during bidding
  • What to do if a bid expires or needs to be reopened
  • What happens when availability changes
  • How to request a different assessment firm
  • What to do when RBA Online shows outdated or unresolved scheduling information
  • When to contact the RBA Help Desk

Quick answer: Is my requested audit date confirmed?

Not necessarily.

When requesting an assessment, the facility may provide a preferred assessment date or acceptable date range. This information supports planning and bidding, but it should not be treated as confirmation that assessors have been booked. 

In the current documented workflow, after RBA selects the winning bid, the assessment progresses to an Input Audit Dates step. The assessment firm submits the audit dates, after which the workflow progresses to Audit Dates Finalized and then to the Scoping Agreement. 

Important: Do not make non-refundable travel arrangements or other commitments based solely on a requested or proposed audit date. Confirm that the assessment has progressed to the appropriate scheduling stage in RBA Online.


Understanding the scheduling process

The general pre-assessment sequence is:

Audit requested → Contracting → Scoping → Bidding → Bid selected → Audit dates finalized → Scoping Agreement → Assessment preparation

 

What this means for facilities

Entering a preferred date when requesting the assessment does not reserve an assessment firm or specific assessors.

Several things still need to occur, including:

  1. Contracting requirements must be completed.
  2. The assessment must be scoped.
  3. Eligible assessment firms must be considered through the applicable bidding process.
  4. A bid must be selected.
  5. Assessment-firm availability must be coordinated.
  6. Audit dates must be finalized.
  7. The applicable Scoping Agreement requirements must be completed.

Who selects the assessment firm?

The RBA Assessment Program Manager (APM) assigns the assessment firm for a VAP.

The APM assigns the assessment firm, and the selected assessment firm then assigns the assessors who will conduct the assessment. For an initial assessment, consider eligible firms with appropriate local expertise. Assessment-firm selection can take into account:

  • Assessment quality
  • Accuracy
  • Professionalism
  • Timeliness
  • Availability
  • Cost 

This distinction is important:

RBA/APM → selects the assessment firm

Selected assessment firm → assigns qualified assessors

The assessment team must also satisfy the applicable RBA assessor requirements. 


Can a facility request a specific assessment firm?

A facility may communicate preferences or concerns about an assessment firm, but providing a preferred firm does not guarantee assignment.

RBA retains responsibility for the applicable firm-selection process. Firm assignment considers factors including qualification, availability, performance, timing, and cost. 

Therefore, a request such as:

"We would prefer Assessment Firm A because the firm has assessors available during our requested dates."

should be treated as a request for consideration, not confirmation of assignment.

Do not consider the assessment assigned to that firm until the VAP workflow reflects the applicable selection.


Can an assessment firm offer available assessors or dates?

Yes. Availability information is useful during assessment planning. An assessment firm may communicate that qualified resources are available for a requested window. Availability is one of the factors considered in firm assignment. 

However:

An offer of assessor availability is not itself an assignment or confirmed audit date.

The assessment must still follow the applicable VAP selection and scheduling workflow.

This prevents different parties from independently making commitments that conflict with the information recorded in RBA Online.


Who assigns the individual assessors?

After an assessment firm is selected, the firm assigns the assessors who will perform the VAP, subject to RBA qualification requirements. 

Facilities therefore generally should not interpret the availability of a particular assessor as confirmation that the assessor has been assigned.

If a particular qualification, language capability, or other assessment requirement is important, communicate that requirement as early as possible so it can be considered during scoping and scheduling.


What happens during bidding?

After scoping is completed, the VAP enters the applicable bidding process. Audit firms then submit bids, and the APM reviews the available bids before selecting the appropriate one. A bid typically provides the information needed to make the assignment decision, including factors related to cost, resources, and availability.


What happens if the requested dates are no longer available?

Availability can change between the initial audit request and final scheduling.

This can happen because:

  • A qualified assessment firm is unavailable during the requested period.
  • Previously available assessors have been assigned elsewhere.
  • The assessment scope changes.
  • Additional assessment requirements are identified.
  • Contracting or signature requirements take longer than anticipated.
  • Scheduling progresses beyond the original requested window.
  • The assessment needs to be rescheduled.

When this occurs, RBA or the applicable assessment firm may need to coordinate an alternative date.

Best practice: Keep the requested audit window as flexible as reasonably possible until the dates are finalized.


What does it mean if a bid has expired?

An expired or outdated bid should not automatically be interpreted as a canceled assessment.

The important question is whether the information used for the original bid remains valid.

Depending on the circumstances, the VAP team may need to:

  • Review the assessment's current status
  • Confirm current assessment-firm availability
  • Reopen or restart bidding
  • Obtain an updated bid
  • Reconfirm proposed audit dates
  • Revisit scoping if assessment information changed
  • Update or revisit the Scoping Agreement if the workflow has already progressed

When might bidding need to be reopened?

Rebidding may be required when information affecting the original bid changes materially.

For example, changes to the assessment scope can affect bidding and the Scoping Agreement downstream. 
 

Possible triggers can therefore include:

  • Material changes in scope
  • Changes affecting required resources
  • Assessment-firm availability
  • Significant scheduling changes
  • Changes that invalidate the assumptions supporting the original bid
  • A need to select another suitable assessment firm

The VAP team should determine whether rebidding is necessary based on the assessment's current workflow state.


What if the bid was already accepted?

Once the assessment has progressed beyond bid acceptance, changing the firm, dates, scope, or cost can affect later workflow stages.

The system provides a Revisit SA function for authorized APM use when the Scoping Agreement needs to be reviewed after the workflow has moved forward. The current workflow specification also allows you to update applicable audit dates as part of that process. 

Therefore, do not attempt to solve a post-SA scheduling change by simply creating a new informal agreement with an assessment firm. The VAP team may need to update the underlying assessment workflow.


Can the assessment firm be changed after assignment?

Potentially, yes, but the change must be handled through the VAP process.

For Priority Closure Assessments, RBA guidance states that the assessment firm that performed the Initial Assessment should be used when viable. Exceptions can include situations where the firm is unavailable during the required assessment window or where there are ethical or potential ethical concerns. 

If you want to request a different firm, contact RBA rather than attempting to coordinate the reassignment directly.


What if I need to reschedule a confirmed assessment?

Contact RBA as early as possible.

Cancellation and rescheduling can have financial consequences once dates are set.

The applicable Auditee Agreement cited in current VAP support materials provides the following conditions:

These terms should always be checked against the agreement applicable to the specific assessment before making a decision. 


What if the date shown in RBA Online appears incorrect or expired?

Do not assume an outdated date represents the current confirmed schedule.

Instead, check:

  1. Audit ID
  2. Current VAP status
  3. Proposed start and end dates
  4. Assigned assessment firm, if shown
  5. Whether bidding has been completed
  6. Whether audit dates have been finalized
  7. Whether the Scoping Agreement has been issued or signed

If these elements conflict, submit a support request.

This is particularly important because an outdated date can reflect a workflow requiring operational review rather than simply a display issue.


Special consideration for semi-announced or unannounced assessments

Do not assume that all assessment types provide the facility with the same scheduling visibility.

RBA Online workflow behavior can differ based on when an assessment was initiated and the applicable workflow. Facilities and assessment firms should therefore follow the instructions and date information provided for the specific assessment rather than using another VAP as a precedent.


How do I know when scheduling is complete?

The strongest indicator is progression through the formal workflow rather than an informal email exchange.

Under the current VAP workflow specification:

Winning bid selected → Audit firm inputs dates → Audit Dates Finalized → Scoping Agreement.

The Scoping Agreement then provides a further contractual confirmation of key assessment information, including the date, cost, and assigned assessment firm. 

Proposed date

A date entered as the preferred assessment window.

Not necessarily confirmed.

Firm availability

An assessment firm indicates that resources are available.

Helpful for planning, but not confirmation.

Bid selected

RBA selects the applicable assessment-firm bid.

Firm selection has progressed, but remaining workflow actions may still be required.

Audit Dates Finalized

The assessment firm has submitted the audit dates and the workflow has progressed.

A significantly stronger scheduling milestone.

Scoping Agreement completed

The contractual assessment information, including applicable date, cost, and firm information, has proceeded through the required SA process.

The assessment can continue to the next applicable preparation stage.


What information should I provide when requesting scheduling assistance?

Providing complete information reduces the need for follow-up and helps the RBA Help Desk route the request to the appropriate VAP resource.

Include:

  • Audit ID
  • Facility name
  • Facility ID, if available
  • Assessment type
  • Current status shown in RBA Online
  • Currently displayed audit date(s)
  • Requested date or date range
  • Assigned assessment firm, if one is displayed
  • Whether a bid has already been accepted
  • Whether the Scoping Agreement has been issued or signed
  • The specific change or confirmation you are requesting
  • Reason for the requested change
  • Screenshot of the relevant RBA Online page, where useful

If you represent an assessment firm

Also provide:

  • Assessment-firm name
  • Proposed dates
  • Confirmation that qualified resources are available
  • Any material scheduling constraints

Avoid sending only:

"Please confirm the audit date."

Providing the Audit ID and current/requested dates makes the request significantly easier to investigate.


Example requests

Confirming a date

Audit ID: G-AU-XXXXXXXX
Facility: [Facility name]
Current date shown: [Date]
Requested window: [Date range]

Could you please confirm whether the audit dates have been finalized? RBA Online currently displays [status], and we want to confirm the schedule before making further arrangements.

Requesting rescheduling

Audit ID: G-AU-XXXXXXXX
Current scheduled dates: [Dates]
Requested new dates: [Dates]

We need to request a change to the scheduled assessment dates because [brief reason]. Please advise whether the change can be accommodated and whether rebidding, a revised Scoping Agreement, or any rescheduling fees would apply.

Assessment firm advising availability

Audit ID: G-AU-XXXXXXXX
Assessment firm: [Firm]
Available dates: [Date range]

Qualified resources are currently available during the dates above. Please confirm whether RBA would like us to proceed with scheduling for this assessment.


Frequently asked questions

I entered a requested date when initiating the VAP. Is that my confirmed audit date?

No. The requested date provides an acceptable or preferred scheduling window. Subsequent scoping, bidding, firm assignment, and audit-date finalization still need to occur. 

Can I choose the assessment firm?

You can communicate a preference, but the APM assigns the assessment firm. Selection considers factors including quality, accuracy, professionalism, timeliness, availability, and cost. 

Can I choose a specific assessor?

Individual assessors are assigned by the selected assessment firm and must meet relevant RBA requirements. 

An assessment firm says it has assessors available. Does that mean the audit is confirmed?

No. Resource availability is useful scheduling information but does not replace RBA's firm-selection and scheduling workflow.

Can bidding be reopened?

Yes, the current workflow provides an APM function to restart bidding when rebidding is required. Whether that is appropriate depends on the assessment's current status and circumstances. 

Can an assessment firm be changed after selection?

A change may be possible, but it must be managed through the VAP process. The required actions depend on the stage of the assessment. 

Does changing the audit date affect the Scoping Agreement?

Potentially. If a Scoping Agreement has already been issued or signed, changes to assessment details may require the SA to be revisited. 

Could changing the date result in additional fees?

Yes. Depending on how close the request is to the scheduled assessment date and the applicable agreement, cancellation or rescheduling costs may apply. 


Need help?

If your assessment's scheduling information appears unresolved, expired, or inconsistent, contact the RBA Help Desk rather than coordinating workflow changes independently.

When requesting assistance, provide the Audit ID, facility name, current status, current dates, requested dates, and the specific action required.

This allows the request to be distinguished quickly between:

  • A date-confirmation request
  • A rescheduling request
  • A rebid request
  • An assessment-firm assignment request
  • An SA revision
  • An RBA Online technical issue

Key takeaway: A preferred date, an assessment firm's availability, and a confirmed VAP schedule are different things. Use the formal RBA Online workflow as the system of record, and request assistance when the displayed status, dates, firm assignment, or Scoping Agreement no longer reflects the expected arrangement.